France Lyon - fr/72 Road
16.03.2010 |
The consortium Spie Sud Est/Yvroud Europeenne des Fluides, Feyzin secured the EUR7.6 million contract for equipment maintenance in the Grand Lyon tunnels, the most important of which are Fourviere (1,850 m), Croix-Rousse (1,750 m), Brotteaux-Servient and Vivier-Merle (336 m). For more, contact Communaute Urbaine de Lyon, fax +33 478 957097, or visit http://marches.grandlyon.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=058386-2010. 11/10...
|
Switzerland Canton of Schwyz - ch/68 Motorways
16.03.2010 |
Gähler und Partner AG of Ennetbaden have secured the EUR2.28 million contract for PM designer for safety refurbishment in 1.14 km-long Mosi tunnel on A4, near Brunnen. Contact OFROU, Zofingen, tel +41 6274575-11, fax -90, e-mail beschaffung.zofingen@astra.admin.ch. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=062920-2010. 11/10...
|
Switzerland Canton Glarus - ch/64 Highway
16.03.2010 |
IG BP2, c/o Bänziger Partner AG of Zurich, secured the EUR2.63 million contract from BAMO for 5.7 km-long N3 Kerenzer tunnel. Contact OFROU, Winterthour, tel +41 522344-711, fax -790, e-mail winterthur@astra.admin.ch. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=062921-2010. 11/10..
|
Italy South Tyrol - it/163 Highway
16.03.2010 |
Construction contract for Kuechelberg tunnel awarded to PAC SpA consortium, value EUR34,695,272 excluding VAT. More from PAC in Capo di Ponte, tel +39 0364331037, fax +39 036442303, e-mail info@pacspa.it and client APB in Bozen, tel +39 04714125-14, fax –39, e-mail gare-11.5@provincia.bz.it Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=071475-2010. 11/10...
|
Italy National - it/158 Railways |
Rete Ferroviaria Italiana SpA is inviting companies to prequalify for civil engineering work on railway tunnels in Italy. Further information and documents from Iacomino Raffaele at Gruppo Ferrovie dello Stato in Milan, tel +39 02637 148-19, fax –20, e-mail dns-qs@rfi.it to whom requests to participate should be sent. Visit
|
Pakistan Karakorum - pk/22 Railway |
Pre-feasibility study being undertaken by ILF Consulting Engineers for construction of single track railway line along the Karakorum highway between the end of the existing railway network in the south at Havelian and the border between Pakistan and China near the famous Khunjrab Pass in the north.
|
China Hong Kong - cn/82 West Island Line |
Prequalification underway by MTR for tender reference no 703 for West Island Line SHW to SYP tunnels value EUR30 million with a view to selective invitations to tender being issued in 4Q/2008 for contract award in 3Q/2009. Expressions of interest to Malcolm O’Neill, tel 3921 3383, e-mail moneill@mtr.com.hk Visit www.mtr.com.hk/eng/tenders/new_projects.html 45/08.
|
|
Awards
Spain Madrid-Barcelona-French border - es/20 High Speed railway |
30.10.2007 |
ADIF has delayed to November the contract award, initially scheduled for 26th October, 2007, for construction of the tunnel that will cross Barcelona between Sants and La Sagrera stations. The decision is the consequence of sinkholes affecting the L'Hospitalet-La Torrassa section. Local commuter services on three suburban lines operated by Renfe and one line operated by the Catalan railways have been interrupted since 20th October. A sixth sinkhole, appeared in Bellvitge station on 26th October, has led to halt work on that section. The work stoppage has amplified the controversy that the Sants-La Sagrera tunnel project has triggered in Barcelona because of the fact that its route passes near the Sagrada Familia cathedral. Read E-News Weekly 45/2007.
The joint venture formed by Sacyr and its subsidiaries Scrinser and Cavosa is the best placed to pocket the contract, with a 35-month construction time (two years and 11 months). This contract consists in constructing a 5.64 km section that will connect the two stations. The first 422 metres and the last 395 metres of the route will be diaphragm wall supported station boxes, while the remaining 4,823 metres will be built by means of a TBM. The project also includes a main shaft situated at the end of the route, two additional shafts for the entrance and exit of the TBM and 12 shafts for emergency exit, five of which will be used also for ventilation and two for pumping of the groundwater.
44/07.
Aldesa Construcciones bagged a EUR82.4 million contract to build the Sarriá del Ter-Sant Julià de Ramis section in Girona. This 5 km stretch includes two tunnels to be excavated by traditional method. The first tunnel, the 3,042 m-long Sarria tunnel, will connect to the previous section, the 1,564 m-long Girona II tunnel, so that trains will travel through a 4,606 m-long tunnel altogether. The second tunnel, the Montagut tunnel, is 475 m long. Visit www.aldesaconstrucciones.es 44/07. |
|
|