France Lyon - fr/72 Road
16.03.2010 |
The consortium Spie Sud Est/Yvroud Europeenne des Fluides, Feyzin secured the EUR7.6 million contract for equipment maintenance in the Grand Lyon tunnels, the most important of which are Fourviere (1,850 m), Croix-Rousse (1,750 m), Brotteaux-Servient and Vivier-Merle (336 m). For more, contact Communaute Urbaine de Lyon, fax +33 478 957097, or visit http://marches.grandlyon.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=058386-2010. 11/10...
|
Switzerland Canton of Schwyz - ch/68 Motorways
16.03.2010 |
Gähler und Partner AG of Ennetbaden have secured the EUR2.28 million contract for PM designer for safety refurbishment in 1.14 km-long Mosi tunnel on A4, near Brunnen. Contact OFROU, Zofingen, tel +41 6274575-11, fax -90, e-mail beschaffung.zofingen@astra.admin.ch. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=062920-2010. 11/10...
|
Switzerland Canton Glarus - ch/64 Highway
16.03.2010 |
IG BP2, c/o Bänziger Partner AG of Zurich, secured the EUR2.63 million contract from BAMO for 5.7 km-long N3 Kerenzer tunnel. Contact OFROU, Winterthour, tel +41 522344-711, fax -790, e-mail winterthur@astra.admin.ch. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=062921-2010. 11/10..
|
Italy South Tyrol - it/163 Highway
16.03.2010 |
Construction contract for Kuechelberg tunnel awarded to PAC SpA consortium, value EUR34,695,272 excluding VAT. More from PAC in Capo di Ponte, tel +39 0364331037, fax +39 036442303, e-mail info@pacspa.it and client APB in Bozen, tel +39 04714125-14, fax –39, e-mail gare-11.5@provincia.bz.it Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=071475-2010. 11/10...
|
Italy National - it/158 Railways |
Rete Ferroviaria Italiana SpA is inviting companies to prequalify for civil engineering work on railway tunnels in Italy. Further information and documents from Iacomino Raffaele at Gruppo Ferrovie dello Stato in Milan, tel +39 02637 148-19, fax –20, e-mail dns-qs@rfi.it to whom requests to participate should be sent. Visit
|
Pakistan Karakorum - pk/22 Railway |
Pre-feasibility study being undertaken by ILF Consulting Engineers for construction of single track railway line along the Karakorum highway between the end of the existing railway network in the south at Havelian and the border between Pakistan and China near the famous Khunjrab Pass in the north.
|
China Hong Kong - cn/82 West Island Line |
Prequalification underway by MTR for tender reference no 703 for West Island Line SHW to SYP tunnels value EUR30 million with a view to selective invitations to tender being issued in 4Q/2008 for contract award in 3Q/2009. Expressions of interest to Malcolm O’Neill, tel 3921 3383, e-mail moneill@mtr.com.hk Visit www.mtr.com.hk/eng/tenders/new_projects.html 45/08.
|
|
Awards
Sweden Stockholm - se/13 Ring Road |
27.01.2008 |
Veidekke has been awarded two contracts for two tunnels and access ramps on the Norra Länken (Northern Link), Stockholm’s north ring road, by the Swedish public roads administration. These contracts are worth a total of just under SEK1 billion. Contract NL 33 is for the Albano rock tunnels, including 1.1 km of one-lane tunnels, 650 metres of two-lane tunnels and 500 metres of three-lane tunnels.
The Albano rock tunnel will require approx. the blasting of 250,000 cubic metres of rock. Contract NL 34 refers to the Teknikhöjden rock tunnels, including 1.5 km of one-lane tunnels and 1,000 metres of two-lane tunnels. The Teknikhöjden rock tunnel will need to blast approx. 300,000 cubic metres of rock. Veidekke previously built the two working tunnels for these tunnels. The work includes jet grouting and shotcreting, construction of concrete bridges and other concrete structures underground, and road construction. Visit www.veidekke.se 05/08.
Oden Anläggning in a 50/50 joint venture with Hochtief bagged contract NL 35 for the Värtan rock tunnels. The assignment includes 200 metres of one-lane tunnels, 650 metres of two-lane tunnels, 250 metres of three-lane tunnels and 1,450 metres of four-lane tunnels. The tunnels will require to move approx. 400,000 cubic metres of rock. The same JV also won contract NL 51 for the Värtan concrete tunnel. Read E-News Weekly 5/2008. The two contracts are worth SEK1.2 million. See also E-News Weekly 1/2008 for the announcement of contract NL 11. Visit www.oden.nu, www.hochtief-construction.de and www.vv.se/templates/page3____19625.aspx 05/08.
|
|
|