France
Lyon - fr/72
Road
16.03.2010
The consortium Spie Sud Est/Yvroud Europeenne des Fluides, Feyzin secured the EUR7.6 million contract for equipment maintenance in the Grand Lyon tunnels, the most important of which are Fourviere (1,850 m), Croix-Rousse (1,750 m), Brotteaux-Servient and Vivier-Merle (336 m). For more, contact Communaute Urbaine de Lyon, fax +33 478 957097, or visit http://marches.grandlyon.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=058386-2010. 11/10...
Switzerland
Canton of Schwyz - ch/68
Motorways
16.03.2010
Gähler und Partner AG of Ennetbaden have secured the EUR2.28 million contract for PM designer for safety refurbishment in 1.14 km-long Mosi tunnel on A4, near Brunnen. Contact OFROU, Zofingen, tel +41 6274575-11, fax -90, e-mail beschaffung.zofingen@astra.admin.ch. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=062920-2010. 11/10...
Switzerland
Canton Glarus - ch/64
Highway
16.03.2010
IG BP2, c/o Bänziger Partner AG of Zurich, secured the EUR2.63 million contract from BAMO for 5.7 km-long N3 Kerenzer tunnel. Contact OFROU, Winterthour, tel +41 522344-711, fax -790, e-mail winterthur@astra.admin.ch. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=062921-2010. 11/10..
Italy
South Tyrol - it/163
Highway
16.03.2010
Construction contract for Kuechelberg tunnel awarded to PAC SpA consortium, value EUR34,695,272 excluding VAT. More from PAC in Capo di Ponte, tel +39 0364331037, fax +39 036442303, e-mail info@pacspa.it and client APB in Bozen, tel +39 04714125-14, fax –39, e-mail gare-11.5@provincia.bz.it Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=071475-2010. 11/10...


Prequalifiers
Italy
National - it/158
Railways
Rete Ferroviaria Italiana SpA is inviting companies to prequalify for civil engineering work on railway tunnels in Italy. Further information and documents from Iacomino Raffaele at Gruppo Ferrovie dello Stato in Milan, tel +39 02637 148-19, fax –20, e-mail dns-qs@rfi.it to whom requests to participate should be sent. Visit
Pakistan
Karakorum - pk/22
Railway
Pre-feasibility study being undertaken by ILF Consulting Engineers for construction of single track railway line along the Karakorum highway between the end of the existing railway network in the south at Havelian and the border between Pakistan and China near the famous Khunjrab Pass in the north.
China
Hong Kong - cn/82
West Island Line
Prequalification underway by MTR for tender reference no 703 for West Island Line SHW to SYP tunnels value EUR30 million with a view to selective invitations to tender being issued in 4Q/2008 for contract award in 3Q/2009. Expressions of interest to Malcolm O’Neill, tel 3921 3383, e-mail moneill@mtr.com.hk Visit www.mtr.com.hk/eng/tenders/new_projects.html 45/08.


Awards

Switzerland
Ceneri - ch/14
High Speed Railway
28.07.2008

The contract for the construction of the Ceneri base tunnel from the northern portal, in Camerino, has been awarded to the Matro sud consortium headed by Pizzarotti teaming up with En­nio Ferrari, LGV, Cossi Costruzioni and Rodio Geotechnik. The consortium presented an offer of CHF103 million for the main northern lot consisting of a tunnel that will emerge on the Vigana hill under highway A2 where a double portal for three tracks will be constructed (two tracks for the new Alptransit railroad and one for the Locarno-Lugano line). Construction is programmed to commence on 6th October, 2008. Visit www.pizzarotti.it, www.ennio-ferrari.ch, www.lgv-sa.ch, www.cossi.com and www.rodio.ch

The project will take place in three phases. First, an approach trench will be built in the slope that, from the valley, will lead to the tunnel site. Then, once the portal area is ready, some 50 metres will be excavated in soft ground just under the A2. From that point, crews will cut the rock through Mount Ceneri on an overall length of about 700 metres consisting of two tubes and a cavern system. The three large caverns, with width up to 23 m and height of 14 m, will be excavated by traditional methods. They will accommodate tracks for the south-north line, the north-south line and the Vigana connection that will be the interchange between north-south high speed lines and the local traffic.  Excavation will take place in soft soil using jet grouting and in rock using explosives. The supports will mainly consist of anchoring bolts, shotcrete, welded mash and steel arches. The final lining will be an inner concrete ring. Visit www.alptransit.ch 29/08.