France Lyon - fr/72 Road
16.03.2010 |
The consortium Spie Sud Est/Yvroud Europeenne des Fluides, Feyzin secured the EUR7.6 million contract for equipment maintenance in the Grand Lyon tunnels, the most important of which are Fourviere (1,850 m), Croix-Rousse (1,750 m), Brotteaux-Servient and Vivier-Merle (336 m). For more, contact Communaute Urbaine de Lyon, fax +33 478 957097, or visit http://marches.grandlyon.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=058386-2010. 11/10...
|
Switzerland Canton of Schwyz - ch/68 Motorways
16.03.2010 |
Gähler und Partner AG of Ennetbaden have secured the EUR2.28 million contract for PM designer for safety refurbishment in 1.14 km-long Mosi tunnel on A4, near Brunnen. Contact OFROU, Zofingen, tel +41 6274575-11, fax -90, e-mail beschaffung.zofingen@astra.admin.ch. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=062920-2010. 11/10...
|
Switzerland Canton Glarus - ch/64 Highway
16.03.2010 |
IG BP2, c/o Bänziger Partner AG of Zurich, secured the EUR2.63 million contract from BAMO for 5.7 km-long N3 Kerenzer tunnel. Contact OFROU, Winterthour, tel +41 522344-711, fax -790, e-mail winterthur@astra.admin.ch. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=062921-2010. 11/10..
|
Italy South Tyrol - it/163 Highway
16.03.2010 |
Construction contract for Kuechelberg tunnel awarded to PAC SpA consortium, value EUR34,695,272 excluding VAT. More from PAC in Capo di Ponte, tel +39 0364331037, fax +39 036442303, e-mail info@pacspa.it and client APB in Bozen, tel +39 04714125-14, fax –39, e-mail gare-11.5@provincia.bz.it Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=071475-2010. 11/10...
|
Italy National - it/158 Railways |
Rete Ferroviaria Italiana SpA is inviting companies to prequalify for civil engineering work on railway tunnels in Italy. Further information and documents from Iacomino Raffaele at Gruppo Ferrovie dello Stato in Milan, tel +39 02637 148-19, fax –20, e-mail dns-qs@rfi.it to whom requests to participate should be sent. Visit
|
Pakistan Karakorum - pk/22 Railway |
Pre-feasibility study being undertaken by ILF Consulting Engineers for construction of single track railway line along the Karakorum highway between the end of the existing railway network in the south at Havelian and the border between Pakistan and China near the famous Khunjrab Pass in the north.
|
China Hong Kong - cn/82 West Island Line |
Prequalification underway by MTR for tender reference no 703 for West Island Line SHW to SYP tunnels value EUR30 million with a view to selective invitations to tender being issued in 4Q/2008 for contract award in 3Q/2009. Expressions of interest to Malcolm O’Neill, tel 3921 3383, e-mail moneill@mtr.com.hk Visit www.mtr.com.hk/eng/tenders/new_projects.html 45/08.
|
|
Case Studies
| Durango Mazatlan |
Download |
The communication and transport ministry (SCT) awarded this summer three contracts worth a total of MXP8.22 billion to complete the final section of the Durango-Mazatlán highway. The first contract was awarded to a consortium led by Mexican construction firm Omega Corp. with a price tag of MXP3.97 billion.
The communication and transport ministry (SCT) awarded this summer three contracts worth a total of MXP8.22 billion to complete the final section of the Durango-Mazatlán highway. The first contract was awarded to a consortium led by Mexican construction firm Omega Corp. with a price tag of MXP3.97 billion. The second contract went to a consortium made up of Spain′s FCC and Mexico′s La Peninsular for MXP2.19 billion. The remaining contract was awarded to Mexico′s Tradeco Industrial for MXP2.06 billion. The first stage of the highway includes a single carriageway, 12 m wide, and the second carriageway will be built in a second phase. The contracts involve only the first stage. Click mx/21.
Given the geography of this mountainous area, the highway requires many tunnels and bridges. Altogether, 57 short single-tube tunnels will be built, representing a total length of 18.3 km. The only tunnel to exceed one kilometre in length is El Sinaloense (2,794 m). To see the list of the tunnels in each contract, click here. Once completed, travel time on the highway will drop from six hours to two and a half hours. 41/08. |
|
|