tunnelintelligence
SICK - gas monitoring       ATKINS       SELI       AMBERG ENGINEERING      
tunnelintelligence
Awards
China
Hong Kong – cn/19
Metro
20.11.2008
The construction contract for the EUR133 million Lai Chi Kok Transfer Scheme, advertised at tunnelbuilder.com earlier this year, has been awarded to Leighton Asia. The project includes two 4.9 m-diameter storm water drainage tunnels with total length of 3.7 km between West Kowloon reclamation and Lai Chi Kok and Sham Shui Po districts, six intake shafts, a stilling basin, an outfall adit into Victoria Harbour, and 270 m of 3 m-diameter connection adits. Work starts immediately for completion in 2012. More from Quinnie Lee, tel +852 2823 1427, e-mail quinnie.lee@leightonasia.com 47/08..
Norway
Akershus – no/105
Dovrebanen
20.11.2008
Contract valued EUR414,000 awarded by Norwegian Railway Infrastructure Administration to Norconsult AS of Sandvika to provide technical and detailed plans of tunnels for the joint project E6 road and Dovrebanen, lot Minnesund-Kleverud, which includes one twin-tube 0.6 km-long road tunnel and 3.1 km of single railway tunnel over a 17 km-long alignment in Eidsvoll and Stange municipalities. ..
Norway
Akershus – no/43
Railway
15.11.2008
Contract for telecommunications installations for 6.5 km section of new double railway track in Baerum municipality for Lysaker-Sandvika, of which 5.5 km in tunnel, awarded by Jernbaneverket to T Connect AS of Manglerud, Oslo. http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=292852-2008 More from Olaf Bjerknes, tel +47 9943 4144, e-mail olbj@jbv.no 46/08. ..
Norway
More & Romsdal – no/76
Road
11.11.2008
Bemel Norge AS of Majorstuen, Oslo has been awarded the contract to supply ventilation fans to the 5.37 km-long Atlantic Ocean tunnel between Kristiansund and Bremnes on National Road 64 in the value EUR555,000...


Prequalifiers
Pakistan
Karakorum - pk/22
Railway
Pre-feasibility study being undertaken by ILF Consulting Engineers for construction of single track railway line along the Karakorum highway between the end of the existing railway network in the south at Havelian and the border between Pakistan and China near the famous Khunjrab Pass in the north.
China
Hong Kong - cn/82
West Island Line
Prequalification underway by MTR for tender reference no 703 for West Island Line SHW to SYP tunnels value EUR30 million with a view to selective invitations to tender being issued in 4Q/2008 for contract award in 3Q/2009. Expressions of interest to Malcolm O’Neill, tel 3921 3383, e-mail moneill@mtr.com.hk Visit www.mtr.com.hk/eng/tenders/new_projects.html 45/08.
Spain
Andalusia - es/155
Road
Prior information notice for construction works, value EUR24.86 million, for a undergroung cut-and-cover tunnel from Pabellon Moises Ruiz to Plaza de Barcelona, 1,1 km, with 0.8 m-thick base, 1.0 m-thick walls and 1.0 m-thick roof, on Carretera de Ronda, in Almeria. The works will include intermodal station.


Several tunnelbuilder reference editions are now available online. To review

Advertise in Spanish!

Subscribe to E-News Weekly

tunnelbuilder demographics in Spanish

Press Releases - sam@tunnelbuilder.com

Jobs

Contact Us - maurice@tunnelbuilder.com

Safety

Road Above Gautrain Tunnel Susides 28.07.2008

While Gauteng province Premier Mbhazima Shilowa attended the unveiling of the first of the Gautrain coaches in England on 8th July, a section of Killarney’s Oxford road collapsed in Rosebank, north of Johannesburg. The collapse created a hole measures about 12 by 8 metres that is filled with water, making it difficult to determine the depth. A precast private residential wall adjacent to the affected surface collapsed but no other buildings were affected. View a video at http://multimedia.thetimes.co.za/videos/2008/07/road-above-gautrain-collapses

The Bombela consortium, the Gautrain construction company, has been instructed to cease excavations in the area where the sinkhole appeared. The order was issued in terms of mine, health and safety legislation. Safety officials were trying to determine if there were any other cracks along the road which could be dangerous. The area was cordoned off and motorists were being diverted off Oxford road. The road is expected to be closed for two weeks. The Johannesburg Roads Agency and the Bombela consortium will be repairing the road over the next two weeks. Bombela and the provincial support team are working together with the city of Johannesburg to provide temporary alternative routes for motorists while the road is being repaired.

The Johannesburg metro police department said the reason for the collapse would be investigated, but that it was very likely that Gautrain construction work going on in that area was the major cause. Construction of the Gautrain tunnel is currently underway beneath the road. Click here.

During routine monitoring process, the TBM technical team noticed surplus material coming through the machine, which is symptomatic of a void being formed above the TBM. Upon investigation they identified water seepage in the TBM chamber and a void above. To give more support to the ground, the TBM’s operational mode was changed to earth pressure balanced mode (EPBM).

At 09:00 a.m., Bombela’s construction team cordoned off the northbound lanes of Oxford road as a precaution and established additional survey monitoring points which were regularly checked. Notwithstanding the further measures put in place a ground loss occurred between the TBM and the utility services above which fractured, causing significant water flow exacerbating the situation and causing the road surface to subside.

At approximately 13:30, an area of Oxford road between North Road and 8th Avenue subsided. An initial void, approximately 6 m x 4 m and 2 m to 3 m in depth, formed at the road surface. This initial subsidence was a consequence of ground loss above the Gautrain TBM, which is currently 12 metres below ground level. No injuries were sustained and no damage occurred to either the TBM or the completed tunnel. The initial hole of 6 m x 4 m increased to 12 m x 7 m as it took approximately two hours for the water mains to be shut down.

Preliminary investigation carried out by Bombela after the event “suggests that water seepage from the utilities (water and effluent pipelines) above the tunnel alignment led to a weakening of the soil being excavated”, causing ground loss directly above the TBM. All steps that could have been, and should have been taken by the construction team were implemented timeously. Since the event, all structures in the vicinity of the subsidence have been continuously monitored and remain stable i.e. surrounding buildings are not at risk. Gautrain representatives said the tunnelling would resume after geotechnical and geological investigations into the collapse are completed, which could take "several weeks". It is not clear how long tunnelling will be delayed by the collapse, which caused water to seep into the tunnel.

Johannesburg Water said it was concerned that “fingers were being pointed” about its water pipes not being sound and that it wanted a copy of Bombela’s preliminary report into the cause of the sinkhole. “When we repaired the broken water main, technicians checked about 100 metres of the pipe for leaks using cameras. They couldn’t find anything” said Johannesburg Water. Johannesburg Water added that if Bombela’s engineers had suspected “seepage from utilities” when they realised a cavity had formed above their tunnel, 12 m below the surface, they should have reported the leak to them. Instead, Bombela changed the setting of the TBM so that it would support the softer soil above it and continued drilling.

Gautrain management said on 9th July that the tunnel collapse on Oxford road would not have any significant impact on the project’s schedule. A Herrenknecht tunnel boring machine is used to complete the 3 km tunnel from Rosebank to Park station because soft rock and waterlogged soil have precluded the use of conventional drilling and blasting methods.

The Gautrain line between Johannesburg, Pretoria and OR Tambo international airport is currently under construction, in one of the biggest infrastructure projects ever seen in South Africa. Construction of the first link in the Gautrain network, between the airport and Sandton in Johannesburg, began in September 2006 and is due to be complete in 2010, with the rest of the network due for completion in 2011. Visit www.gautrain.co.za 29/08.

Gautrain_1.jpg

Gautrain_2.jpg

click to view Ceresola TLS company profile

xella

Schoema

click to view IPS company profile

IWMA

otb

Atkins

Marioff