tunnelintelligence
tunnelintelligence
Awards
France
Lyon - fr/72
Road
16.03.2010
The consortium Spie Sud Est/Yvroud Europeenne des Fluides, Feyzin secured the EUR7.6 million contract for equipment maintenance in the Grand Lyon tunnels, the most important of which are Fourviere (1,850 m), Croix-Rousse (1,750 m), Brotteaux-Servient and Vivier-Merle (336 m). For more, contact Communaute Urbaine de Lyon, fax +33 478 957097, or visit http://marches.grandlyon.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=058386-2010. 11/10...
Switzerland
Canton of Schwyz - ch/68
Motorways
16.03.2010
Gähler und Partner AG of Ennetbaden have secured the EUR2.28 million contract for PM designer for safety refurbishment in 1.14 km-long Mosi tunnel on A4, near Brunnen. Contact OFROU, Zofingen, tel +41 6274575-11, fax -90, e-mail beschaffung.zofingen@astra.admin.ch. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=062920-2010. 11/10...
Switzerland
Canton Glarus - ch/64
Highway
16.03.2010
IG BP2, c/o Bänziger Partner AG of Zurich, secured the EUR2.63 million contract from BAMO for 5.7 km-long N3 Kerenzer tunnel. Contact OFROU, Winterthour, tel +41 522344-711, fax -790, e-mail winterthur@astra.admin.ch. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=062921-2010. 11/10..
Italy
South Tyrol - it/163
Highway
16.03.2010
Construction contract for Kuechelberg tunnel awarded to PAC SpA consortium, value EUR34,695,272 excluding VAT. More from PAC in Capo di Ponte, tel +39 0364331037, fax +39 036442303, e-mail info@pacspa.it and client APB in Bozen, tel +39 04714125-14, fax –39, e-mail gare-11.5@provincia.bz.it Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=071475-2010. 11/10...


Prequalifiers
Italy
National - it/158
Railways
Rete Ferroviaria Italiana SpA is inviting companies to prequalify for civil engineering work on railway tunnels in Italy. Further information and documents from Iacomino Raffaele at Gruppo Ferrovie dello Stato in Milan, tel +39 02637 148-19, fax –20, e-mail dns-qs@rfi.it to whom requests to participate should be sent. Visit
Pakistan
Karakorum - pk/22
Railway
Pre-feasibility study being undertaken by ILF Consulting Engineers for construction of single track railway line along the Karakorum highway between the end of the existing railway network in the south at Havelian and the border between Pakistan and China near the famous Khunjrab Pass in the north.
China
Hong Kong - cn/82
West Island Line
Prequalification underway by MTR for tender reference no 703 for West Island Line SHW to SYP tunnels value EUR30 million with a view to selective invitations to tender being issued in 4Q/2008 for contract award in 3Q/2009. Expressions of interest to Malcolm O’Neill, tel 3921 3383, e-mail moneill@mtr.com.hk Visit www.mtr.com.hk/eng/tenders/new_projects.html 45/08.


Safety

Experts Say Channel Tunnel Fire Made Worse by Open Wagons 29.09.2008

Tunnel operator Eurotunnel was criticised for failing to replace open sided lattice framed lorry carriers with enclosed rolling stock. The tunnel operator was also attacked for failing to install fire suppression systems in the lorry wagons and for failing to provide adequate protection to the tunnel's concrete lining.

A prototype on-board fire suppression system was developed and tested by Eurotunnel over six years after the November 1996 fire. This system involved installing a water tank at one end of the shuttle train with pumps and pipes able to distribute water to the wagons in a fire. Eurotunnel abandoned the development of the system concluding that it would be unreliable, expensive to maintain and would deliver few safety benefits.

British Fire Brigades Union (FBU)

After the fire, the British Fire Brigades Union (FBU) claimed recommendations it made 12 years ago following the Channel tunnel fire in November 1996 were ignored. That fire burned for seven hours and caused GBP200 million of damage to the tunnel.

FBU south east general secretary Jim Parrott said: "We submitted a report after the last major fire 12 years ago, and our main concern was open-sided wagons. We wanted closed trucks that would contain any fire. Considering there are 40,000 vehicle fires per year in the UK, it is remarkable there have not been more fires in the Channel tunnel since." Eurotunnel uses open-sided wagons to transport HGVs through the Channel tunnel.

"In an open-sided wagon, any fire will be fanned by the speed of the train. In a closed wagon, you would take people away from their vehicles, and if a fire is detected, you could then fill a truck with either an inert gas or compressed air foam, both of which are very efficient at putting out fires, and more compact than water-based systems," he said.

August 1996 fire report

The official Rail Accident Investigation Branch report into a less serious fire in August 2006 also cited the lack of fire suppression. "The current design of the carrier wagons would not prevent the spread of the fire to involve many HGVs (as was the case in the fire in November 1996). A fire of this type could cause major structural damage to the tunnel and disruption of the tunnel's mechanical and electrical systems. It is most unlikely that intervention by fire fighters would significantly control or limit the damage caused. In order to prevent the spread of fire between carrier wagons it would be necessary to adopt containment of the carrier wagons, an on-board fire suppression system, or a combination of the above," says the report.

Eurotunnel’s stance

Eurotunnel defended the company's approach: "No safety case was made to install covered wagons. From the perspective of fire protection and fire safety, it would be harder to get into a covered wagon, and the properties of the cover would negate its purpose."

The Channel tunnel operator defended the lack of on-board fire suppression systems and highlighted the presence of fire detectors. "There are no on-board sprinklers. There are smoke particle and flame detectors. If a fire is found, then the procedure is we stop the train and move passengers and use the fire and rescue services. Sprinkler systems are not considered by all the safety experts to be the adequate solution and are not a significant improvement on what is already there."

Damage extent

Damage to the tunnel is likely to be far worse than in November 1996, when the section of damaged tunnel was closed for six months. The fire burnt for six to seven hours and there was significant spalling. Half the concrete came away over a significant length.

According to fire chiefs, the damage done to the tunnel fire is so bad that is likely to be at least six months before it fully reopens and could take longer. They regard the blaze as far worse than the one in November 1996.

At a meeting gathering members of the Kent and Medway Fire Authority, councillors from Kent county council and Medway council, graphic photographs of the damage taken by fire fighters at the scene were shown. The photographs distributed reveal the fire's intensity was such that, in some parts, it completely stripped away the tunnel lining back to the supporting steel structures.

Meanwhile, the first of three 17 km sections in the north tunnel reopened on 15th September, with a second on 17th September. But it could be some time before the final 17 km stretch of track reopens. When it reopens depends on how quickly the work can be done.

There have now been three major fire incidents in 12 years when the original risk assessment, made at the time the tunnel opened, suggested there would be one every thousand years. Click here. 39/08.